Linwood Avenue Bridge to open to traffic

LINWOOD AVENUE BRIDGE TO OPEN TO TRAFFIC


Beginning Tuesday, August 7, the bridge located at Linwood Avenue south at the intersection of Southern Loop will be open to traffic.


The bridge project, originally estimated to take 120 days, has been completed two weeks ahead of schedule and under bid. The bridge was previously closed to allow the Caddo Parish Department of Public Works to replace the structure, ensuring decades of safety and sustainability for motorists.


With the completion of the Linwood Avenue Bridge project, the Parish's live Project CAM will be moving to the Earl G. Williamson Park in Oil City. Residents can access this live, around the clock feed by visiting www.caddo.org .

Facebook Twitter Email

Other News in General

Caddo Commission Legislative Recap

Posted on: April 5, 2021
winter weather update

ASMC emergency call line restored

Posted on: February 17, 2021
ppe

Small Business COVID Kit Application

Posted on: February 8, 2021
icyroads

Parish of Caddo Weather Closures

Posted on: January 10, 2021
Parish Seal (2)

Caddo Commission adopts 2021 budget

Posted on: December 4, 2020
bridge open

Pine Hill Road bridge now open to traffic

Posted on: September 14, 2020
Hurricane-Laura

Parish of Caddo closures

Posted on: August 26, 2020
Be Smart Be Prepared poster

September is National Preparedness Month

Posted on: September 4, 2018

2018 Tax Renewal Trifold

Posted on: August 13, 2018